Bridge across railway and Rojek Pond, Motorway D47, section 08

Completed in 2007

The twin bridge, with a total length of 580.0 m and spans from 28.6 to 69.5 m, has a deck assembled from steel plate girders and a composite deck slab. The plate girders are indirectly supported by pier diaphragms. The steel structure was progressively – span - by -span – assembled on the ground and subsequently lifted into the design position.

SHP: design for construction permission
          bid design
          detailed design