Bridge across the Rokytka Creek in Prague

Completed in 1987

Bridge of eleven spans, with lengths from 24.70 to 36.00 m, has a deck assembled from precast and match cast segments with a double-tee cross section. The deck was erected in a progressive cantilever from one abutment to another.

Design: Pudis, Prague
Jiri Strasky: Conceptual design, development of the segmental structure.
Ilja Husty: Project engineer for construction engineering.