Bridge across the Vrsovice switching yard, Prague

Completed in 1993

The bridge of nine spans, with lengths from 26.40 to 101.20 m, is formed by a box girder with a width of 29.50 m assembled from precast segments and additionally cast overhangs supported by precast struts. The main span is suspended on a single pylon situated in the bridge axis.

Design: Design office of Dopravni stavby Olomouc.
Jiri Strasky: Author of design, chief design engineer.
Ilja Husty: Project engineer.